推荐的夹板间距

150The following illustration shows the tensile strength required by each cable cleat depending upon fixing centres/intervals.

= 0.17/ s.
=电缆导体上的最大力(n / m)

0.17 (190 x 190) / (36 / 1000) = 170,477.22 N/m
Cable Ø = 36mm= 190ka.
安装间隔:每根电缆夹板300mm(x 0.3)= 51,141.67N

0.17 (190 x 190) / (36 / 1000) = 170,477.22 N/m
Cable Ø = 36mm电缆夹板间距计算= 190ka.
安装间隔:600mm(x 0.6)=每根电缆夹板102,283.33N。
Each cable cleat in this configuration must restrain two times the force
of those in the above configuration (300mm).

0.17 (190 x 190) / (36 / 1000) = 170,477.22 N/m
Cable Ø = 36mm= 190ka.
安装间隔:900mm(x 0.9)=每根电缆夹板153,424.00N。
这种配置中的每个电缆夹板必须抑制上面的力的一半和半倍
配置(600mm),或第一个配置(300mm)中的力的三倍。